Brunswick Elementary School Replacement

BES Architecture Drawing

Contact

Brad Ahalt
Senior Project Manager

(301) 644-5164

September 8, 2021 presentation to the Board of Education

Date: January 12, 2022
Project: Brunswick Elementary School – New Construction
Architect: GWWO Architects
Construction Manager: Keller Construction CM@R
Re: Project Update for Website
Project #36021

Project Timeline

  1. Project Scope / Description
    1. New Elementary School to replace the existing Elementary School on the existing site
    2. New Elementary School Building is 96,475 Total SF
  2. Project Schedule
    1. Design - Complete
    2. Bidding – Complete
    3. Pre-Construction
      1. Submitted for Final Approvals of the following items:
        1. Site Plan
        2. Improvement Plan
        3. Zoning Certificate
        4. Public Works Agreement
        5. Grading Permit
        6. Building Permit
    4. Construction
      1. New School Construction Stage 1 – April 2022 – June 2023
      2. New School Construction Stage 1 Substantial Completion – June 30, 2023
      3. New School Construction Stage 1 Occupancy – August 2023
      4. Existing School Demolition and Site Restoration Construction Stage 2 – July 2023 – April 2024
    5. Project Completion Construction Stage 1 and 2 – June 2024
  3. Project Budget
    1. Total Project Budget – TBA
    2. Construction Budget – TBA
  4. Current Status
    1. Contracts have been awarded.
    2. Waiting on Final Permit Approvals in order to begin construction in April 2022.