Brunswick Elementary School Replacement
Contact
Brad Ahalt
Senior Project Manager
(301) 644-5164
Date: January 12, 2022
Project: Brunswick Elementary School – New Construction
Architect: GWWO Architects
Construction Manager: Keller Construction CM@R
Re: Project Update for Website
Project #36021
Project Timeline
- Project Scope / Description
- New Elementary School to replace the existing Elementary School on the existing site
- New Elementary School Building is 96,475 Total SF
- Project Schedule
- Design - Complete
- Bidding – Complete
- Pre-Construction
- Submitted for Final Approvals of the following items:
- Site Plan
- Improvement Plan
- Zoning Certificate
- Public Works Agreement
- Grading Permit
- Building Permit
- Submitted for Final Approvals of the following items:
- Construction
- New School Construction Stage 1 – April 2022 – June 2023
- New School Construction Stage 1 Substantial Completion – June 30, 2023
- New School Construction Stage 1 Occupancy – August 2023
- Existing School Demolition and Site Restoration Construction Stage 2 – July 2023 – April 2024
- Project Completion Construction Stage 1 and 2 – June 2024
- Project Budget
- Total Project Budget – TBA
- Construction Budget – TBA
- Current Status
- Contracts have been awarded.
- Waiting on Final Permit Approvals in order to begin construction in April 2022.