Green Valley Elementary School Replacement
Project Updates
Brad Ahalt Senior Project Manager 240-586-8455 |
FCPS Website Construction Project Updates, January 10, 2025
Architect: GWWO Architects
Construction Manager: Dustin Construction CM@R
- Project Scope / Description
- New Elementary School in Landsdale Development to replace the existing Elementary School
- New Elementary School Building is 96,364 Total SF
- Project Schedule
- Design - Complete
- Bidding – Complete
- Pre-Construction
- Construction
- New School Construction Stage 1 – May 2024 – July 2025
- New School Construction Stage 1 Substantial Completion – July 2025
- New School Construction Stage 1 Occupancy – August 2025
- Existing School Demolition and Site Restoration Construction Stage 2-August 2025–December 2025
- Project Completion Construction Stage 1 and 2 – December 2025
- Project Budget
- Total Project Budget – TBA
- Construction Budget – TBA
- Current Status
- Construction is ongoing with Project completion at 45%