Valley Elementary School Replacement
Project Updates

Brad Ahalt
Senior Project Manager

240-586-8455

FCPS Website Construction Project Updates, January 10, 2025

Project: Valley Elementary School – New Construction
Architect: GWWO Architects
Construction Manager: Dustin Construction CM@R

  1. Project Scope / Description
    1. New Elementary School in Landsdale Development to replace the existing Elementary School
    2. New Elementary School Building is 102,320 Total SF
  2. Project Schedule
    1. Design - Complete
    2. Bidding – Complete
    3. Pre-Construction
    4. Construction
      1. New School Construction Stage 1 – May 2024 – July 2025
      2. New School Construction Stage 1 Substantial Completion – July 2025
      3. New School Construction Stage 1 Occupancy – August 2025
      4. Existing School Demolition and Site Restoration Construction Stage 2-August 2025–December 2025
      5. Project Completion Construction Stage 1 and 2 – December 2025
  3. Project Budget
    1. Total Project Budget – TBA
    2. Construction Budget – TBA
  4. Current Status
    1. Construction is ongoing with Project completion at 55%