Oakdale Middle School Addition
Project Schedule
Phase | Duration |
---|---|
Design | December 2019 - April 2020 |
Combined DD/CD Presentation | March 2020 |
Bid and GMP Approval | April 2020 - May 2020 |
Construction | June 2020 - August 2021 |
Student Occupancy | August 2021 |
Active Occupied Experience: Ensuring Safety
- Safe separation student/staff - careful measures will be taken to maintain a safe separation between construction and ongoing school activities
- Coordination & Communication - close coordination with school and consistent communication of project schedule and activities to all affected school personnel, including building maintenance
- Noise reduction - Keller will minimize noise as much as possible during school operating hours. Additionally, we will coordinate the construction schedule with the school's testing schedule to avoid impacting testing times
- Dust control and Indoor Air Quality (IAQ) measures
- Proper Authorization of Workers On-Site - proper authorization of all construction personnel on-site
- Security - identification badges for all workers
- Pedestrian/traffic control - pedestrian and traffic control measures as needed
- Close coordination with school events calendar including athletics, academic, and social events
Communications with the Oakdale Community
- Keller is committed to keeping the Oakdale Middle School (OMS) community informed of design and construction activities and progress
- Our goal is to build a relationship of trust and transparency with the Oakdale Middle School community
- Keller will provide retular updates to FCPS to share with the OMS community
- OMS web page - construction update page
- FCPS web page update is in progress
- OMS can send updates via FindOutFirst (FOF)